Fukushima Roadmap.
The roadmap for controlling and cleaning up the accident at the Fukushima Nuclear Power Station is evidently out. I don’t have direct access but NHK is reporting:
o Removal of the melted fuel rods may begin in 10 years (2021).
o The 2021 target date depends on timely development of new technology.
o On-site buildings will be demolished and safely cleared away in “dozens of years”.
There is no statement about when the accident is expected to end.o There are still daily uncontrolled releases of radiation to the environment.
o The reactors are not yet in “cold shutdown” (and probably will not be for some months).
o Reactor 3 is the most temperamental and is prone to temperature excursions when the input rate of cooling water is reduced.